National University Earned Value Worksheet

National University Earned Value Worksheet

Question Description

I’m working on a engineering test / quiz prep and need an explanation and answer to help me learn.

Question 1/ Multiple-Select: Select all that apply correctly for this problem.

A PERT project’s total time Te (or ‘μ’ ) estimate to complete (for the critical path is) 16.0 weeks with a variance of 1.0. The following ‘Z’ values apply for completing the project at different intervals.

Question 2 options:

The z value for completing the project in 15 weeks is -1.0

The z value to complete the project in 18 weeks is 2.0

The z value to complete the project in 17 weeks is 1.5

The z value to complete the project in 19 weeks is 3.0

Question2/ Given a PERT project Te (or μ ) is 100 days, with a variance of 10,

the probability to complete the project in 105 days is:

95.00%

95.25%

94.95%

95.35%